Re: MRP for Maintenance Order

$
0
0

Thanks Singh,

 

 

We have try to use setting like your suggestion.

It's OK for fast moving spare part that we manage the stock with safety stock.

We not use reorder point for MRP.

 

 

One of the problem is came from following case scenario:

1. Maintenance section create Corrective Maintenance Order

2. That MO use component which is slow moving part

3. Stock of slow moving part is not managed, safety stock is zero

4. When Warehouse runs MRP, there is PR created to purchase the requested material from MO.

5. Whie the material in procurement process, the equipment is urgently to be fixed. And Maintenance Section try to use any possible replacement part and it works.

6. After the equipment can be operated after fixing, The Maintenance Section want to TECO the MO but it can't be done until requested component sets Final Issue

7. Then Maintenance section sets Final Issue the requested material of MO which in the same time, this material is in procurement progress.

8. When procurement done and the material is received, it will not be issued to MO which request it because MO has been TECO. This material will keep in stock and will problem to Warehouse section due to stock level and space

 

 

Any idea about case scenario above?

 

 

Thanks

Adi