Hi Jansi
Of course I'm not going to change this for GO LIVE. As per my previous reply, I want to change this for TEST phase. At the moment CR's can be created during test phase (for implementation proejcts)...but this shouldn't be allowed as we should be using ZMTM (defect corrections) if changes are still required whilst in Test phase. Not sure why standard ChaRM allows this??
As per your recommendation I have gone into the action profile...I don't see anywhere where I can dicate that an implementation project cannot have a CR assigned during Test phase:
This is getting fairly urgent as I don't want to go live with ChaRM (in 7.1) until this is sorted? If anyone has any advice please let me know....looks like I may have to raise an OSS incident with SAP.
Cheers
Shaun